CORRECT AUTHORIZED PSP CERTIFICATION & GUARANTEED ASIS PSP EXAM SUCCESS WITH RELIABLE TEST PSP DURATION

Correct Authorized PSP Certification & Guaranteed ASIS PSP Exam Success with Reliable Test PSP Duration

Correct Authorized PSP Certification & Guaranteed ASIS PSP Exam Success with Reliable Test PSP Duration

Blog Article

Tags: Authorized PSP Certification, Test PSP Duration, New PSP Dumps Free, Test PSP Result, PSP Flexible Testing Engine

The ASIS PSP certification exam is a terrific and quick way to develop your profession. With just one ASIS PSP exam, you can significantly advance both personally and professionally. One of the greatest methods to advance your skills is to sign up for the ASIS PSP Certification Exam and devote all of your efforts to successfully passing the ASIS PSP exam.

The PSP certification exam covers a broad range of topics related to physical security, including risk assessment, security planning and design, emergency management, and investigations. It is a rigorous exam that tests the knowledge and skills of candidates in these areas, and passing the exam demonstrates a high level of expertise in physical security management.

The PSP Exam covers a wide range of topics related to physical security, including risk analysis, threat assessment, security design, security operations, and emergency management. PSP Exam is designed to be challenging and comprehensive, and it requires a significant amount of preparation and study to pass. ASIS Physical Security Professional Exam certification is ideal for individuals who are seeking to advance their careers in the field of physical security or for those who are looking to demonstrate their expertise and credibility to employers.

>> Authorized PSP Certification <<

Pass Guaranteed Efficient ASIS - Authorized PSP Certification

As one of the most professional dealer of practice materials, we have connection with all academic institutions in this line with proficient researchers of the knowledge related with the PSP Practice Exam to meet your tastes and needs, please feel free to choose. We want to specify all details of various versions. You can decide which one you prefer, when you made your decision and we believe your flaws will be amended and bring you favorable results even create chances with exact and accurate content.

ASIS PSP (ASIS Physical Security Professional) exam is a globally recognized certification program for security professionals who specialize in physical security. PSP exam is designed to validate the knowledge and expertise of professionals in the field of physical security and to enhance their credibility and value in the industry. The ASIS PSP Certification program is offered by ASIS International, the world's largest membership organization for security professionals.

ASIS Physical Security Professional Exam Sample Questions (Q146-Q151):

NEW QUESTION # 146
If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

  • A. Has yet to be completed.
  • B. Is a milestone.
  • C. It is on the critical path.
  • D. Was completed in the past.

Answer: A

Explanation:
Negative total float occurs when an activity's scheduled completion date extends beyond the project deadline due to constraints. This condition indicates that the activity is still pending and needs immediate attention to avoid further delays.
* Option A (milestone) is unrelated.
* Option B (critical path) is not necessarily true, as activities with negative float can exist off the critical path under certain constraints.
* Option C (completed in the past) is incorrect as negative float applies only to future or ongoing activities.


NEW QUESTION # 147
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

  • A. Use the progressed portion of the critical path of the baseline schedule.
  • B. Use the progressed portion of the critical path of all the updates previous to the current update.
  • C. Use the forward-looking critical path of the most current updates.
  • D. Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.

Answer: B

Explanation:
Understanding As-Built Critical Path Analysis:
* Determining the as-built critical path of a project involves identifying the sequence of activities that actually dictated the completion of the project. This is especially important in projects that are underway, as schedules often deviate from the original baseline due to progress updates and unplanned changes.
* Explanation of Each Option:
* A. Use the progressed portion of the critical path of all the updates previous to the current update:
This is correct. To determine the most likely as-built critical path, analyzing the progressed portion of the critical path from all previous updates provides the most accurate representation of the project's actual execution. By reviewing the progression over time, you can piece together the actual sequence of critical activities.
* B. Use the progressed portion of the critical path of the baseline schedule:This is incorrect. The baseline schedule reflects the original plan, which may no longer be accurate due to progress deviations, delays, or changes in logic. Using the baseline alone does not account for the dynamic nature of the project.
* C. Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate:This is incorrect. While project personnel may provide insights, relying solely on subjective opinions introduces biases and inconsistencies. A properly maintained and updated schedule is far more reliable for determining the critical path.
* D. Use the forward-looking critical path of the most current updates:This is incorrect. The forward- looking critical path only reflects what is expected to happen from the current point onward. It does not provide an accurate representation of the as-built critical path up to the current point.
Study Guide References:
* The PSP Study Guide emphasizes the importance of analyzing progress updates to trace the actual sequence of critical activities. Section 2.3.2 (Tracking Schedule Progress) discusses the role of historical updates in understanding project performance.
* The guide also highlights that a proper as-built analysis requires a review of all updates to identify shifts in the critical path over time.


NEW QUESTION # 148
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?

  • A. 12.
  • B. 14.
  • C. Cannot be determined.
  • D. 13.

Answer: A

Explanation:
To determine how many activities in the "normal" schedule would be affected by the constraint of no activity exceeding a two-month duration (approximately 60 days):
* Review the "Normal Schedule Days" Column:Look for activities with a duration greater than 60 days in the "Normal Schedule Days" column of the table provided in the image.
* Count the Affected Activities:Count all activities where the "Normal Schedule Days" value exceeds
60.
Activities with durations greater than 60 days:
* Activity ID 1000: 1072 days
* Activity ID 1001: 85 days
* Activity ID 2001: 92 days
* Activity ID 3001: 152 days
* Activity ID 4001: 152 days
* Activity ID 5001: 102 days
* Activity ID 6001: 140 days
* Activity ID 6002: 115 days
* Activity ID 6003: 152 days
* Activity ID 9001: 175 days
* Activity ID 9002: 180 days
* Activity ID 9005: 72 days
Total Count:
There are 12 activities in the "normal" schedule exceeding the 60-day duration constraint.
Verified answer:A. 12.
Detailed Explanation with References: The constraint specifies that no activity should exceed a two-month (60-day) duration. By examining the "Normal Schedule Days" column, any activity with a duration greater than 60 days is non-compliant and therefore affected. The PSP study guide emphasizes reviewing contract requirements to ensure schedules adhere to such administrative constraints.


NEW QUESTION # 149
Which of the following is NOT the organizational level of international terrorism?

  • A. Modern terrorism
  • B. Individual terrorism
  • C. State terrorism
  • D. Group terrorism

Answer: A


NEW QUESTION # 150
Decentralizing a procedure or operation so that a security or safety problem at one location will not cause a complete loss is called:

  • A. Risk spreading
  • B. Risk production
  • C. Risk protection
  • D. Risk diffusion

Answer: A


NEW QUESTION # 151
......